WSPI 1, $7.5-million water project—going from “bridge” loan to 40-year loan

The U. S. Department of Agriculture used to give 40-year low-interest loans up front to its recipients.  

Now the USDA makes the City of T or C take out a three-year “bridge” loan from a local bank, greatly complicating matters and slowing down projects. 

When the city burns through the bridge loan, the USDA will then pay it off and turn the debt into a 40-year loan. It then also releases the grant money. 

Bridge loans siphon off money for interest payments that would otherwise go to construction, making projects smaller and more expensive. 

The USDA rule is that the bridge-loan money must be spent first before the grant money kicks in.

At the Nov. 18 city commission meeting, City Manager Gary Whitehead said the city has spent all but about $1 million of the bridge loan for the Water Systems Performance Improvements I project or WSPI 1. 

WSPI 1 is a $2.72 million grant, a $4.811 million loan or $7.531 million project. 

The city took out a $4.811 bridge loan with Bank of the Southwest at 5.5 percent interest about a year ago. 

Now it is time to have the USDA take over the bridge loan and to convert it to a 40-year loan. 

Whitehead presented the USDA’s  $4.811 million “revenue bond” for “publication” at the recent meeting. The 40-year debt carries a 1.375 percent yearly interest rate.

State law requires that such revenue-bond debt go to a public hearing, hence the needed city-commission approval of legal-ad publication in the Sentinel newspaper, which it granted unanimously. 

The public hearing will probably occur at the Dec. 16 meeting.

Whitehead said the water department has now reached its limit, having accrued about $750,000 a year in debt payments.    

Rate payers are carrying the load via yearly increases. They were tied to the Consumer Price Index in 2019, which varied from a whopping 10 percent to about 3 percent in recent years. That changed about four months ago. The city commission approved a flat 5 percent yearly increase starting July 2027. 

The USDA awarded the city the WSPI 1 loan/grant way back in 2021, demonstrating how long it takes these big water projects to work through USDA’s design and financing hoops and hurdles.  

WSPI 1 will tame the city’s high/low water-pressure problems–the cause of many water leaks. Eight pressure relief valves will be installed, setting up controllable water zones. It will also replace the water line that runs from the Cook Street Station to the Morgan Street Booster Station. Cook Street receives the city’s well output, six wells in all. There the water is treated with chlorine and then sent to the first booster station, Morgan Street. Other water lines will also be replaced, nearly three miles of line in all. 

TAGS

Share This Post
Kathleen Sloan
Kathleen Sloan

Kathleen Sloan has been a local-government reporter for 17 years, covering counties and cities in three states—New Mexico, Iowa and Florida. She has also covered the arts for various publications in Virginia, New Mexico and Iowa. Sloan worked for the Truth or Consequences Herald newspaper from 2006 to 2013; it closed December 2019. She returned to T or C in 2019 and founded the online newspaper, the Sierra County Sun, with Diana Tittle taking the helm as editor during the last year and a half of operation. The Sun closed December 2021, concurrent with Sloan retiring. SierraCountySun.org is still an open website, with hundreds of past articles still available. Sloan is now a board member of the not-for-profit organization, the Sierra County Public-Interest Journalism Project, which supported the Sun and is currently sponsoring the Sierra County Citizen, another free and open website. Sloan is volunteering as a citizen journalist, covering the T or C beat. She can be reached at kathleen.sloan@gmail.com or 575-297-4146.

Posts: 290

Leave a Comment

Your email address will not be published. Required fields are marked *

Comment Fields

Please tell us where you live. *

This site uses Akismet to reduce spam. Learn how your comment data is processed.